ITAC Assessment: TN0639
ITAC logo
ITAC Assessment: TN0639
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Inner springs for bed mattresses and spring sets for sleeper
NAICS
n/a
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 150,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,397 2,106,682
kWh
Electricity Demand $44,505 4,760
kW-mo/yr
Electricity Fees $(-4.0) -
LPG $106,122 23,203
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $86,834 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $86,364

Recommendations

# Description Yearly Savings* Imp'd Cost* Status LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 4.611: Begin a practice of predictive / preventative maintenance $74,290 $26,180 - - $(-40,000.0) - $114,290
02 2.7261: Install timers and/or thermostats $5,440 $3,440 $5,440
-
MMBtu
- - - -
03 3.5248: Separate and recycle scrap metal to foundry or for sale $4,680 - - $4,680
-
lb
- - -
04 3.5311: Recover and reuse waste material $1,200 - - - - $1,200 -
05 2.2437: Recover waste heat from equipment $754 $950 $754
-
MMBtu
- - - -
06 2.2515: Use optimum thickness insulation $470 $1,125 $470
-
MMBtu
- - - -
TOTAL RECOMMENDED $86,834 $31,695 $6,664
-
MMBtu
$4,680
-
lb
$(-40,000.0) $1,200 $114,290
TOTAL IMPLEMENTED $86,364 $30,570 $6,194
-
MMBtu
$4,680
-
lb
$(-40,000.0) $1,200 $114,290
Yearly Savings* Imp'd Cost* LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs