Assessment Year | 1998 |
---|---|
Principal Product | Inner springs for bed mattresses and spring sets for sleeper |
NAICS |
n/a
|
SIC | 3429: Hardware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
150,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $91,397 | 2,106,682 |
kWh
|
$0.043 |
Electricity Demand | $44,505 | 4,760 |
kW-mo/yr
|
$9.35 |
Electricity Fees | $(-4.0) | - |
|
- |
LPG | $106,122 | 23,203 |
MMBtu
|
$4.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $86,834 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $86,364 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.611: Begin a practice of predictive / preventative maintenance | $74,290 | $26,180 | - | - | $(-40,000.0) | - | $114,290 | |
02 | 2.7261: Install timers and/or thermostats | $5,440 | $3,440 |
$5,440
-
MMBtu
|
- | - | - | - | |
03 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $4,680 | - | - |
$4,680
-
lb
|
- | - | - | |
04 | 3.5311: Recover and reuse waste material | $1,200 | - | - | - | - | $1,200 | - | |
05 | 2.2437: Recover waste heat from equipment | $754 | $950 |
$754
-
MMBtu
|
- | - | - | - | |
06 | 2.2515: Use optimum thickness insulation | $470 | $1,125 |
$470
-
MMBtu
|
- | - | - | - | |
TOTAL RECOMMENDED | $86,834 | $31,695 |
$6,664
-
MMBtu
|
$4,680
-
lb
|
$(-40,000.0) | $1,200 | $114,290 | ||
TOTAL IMPLEMENTED | $86,364 | $30,570 |
$6,194
-
MMBtu
|
$4,680
-
lb
|
$(-40,000.0) | $1,200 | $114,290 | ||
Yearly Savings* | Imp'd Cost* | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs