| Assessment Year | 1998 |
|---|---|
| Principal Product | Chopped Fiber Glass |
| NAICS |
n/a
|
| SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 230 |
| Plant Area |
362,000
ft2
|
| Annual Production | 120,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $3,354,612 | 140,894,492 |
kWh
|
$0.024 |
| Electricity Demand | $1,117,834 | 206,581 |
kW-mo/yr
|
$5.41 |
| Electricity Fees | $(-25,036.0) | - |
|
- |
| Natural Gas | $2,034,184 | 685,461 |
MMBtu
|
$2.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $608,611 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,830 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.5313: Increase amount of waste recovered for resale | $494,000 | $32,000 | - | - |
$190,000
-
lb
|
- | $304,000 | |
| 02 | 3.3128: Utilize other methods to remove contaminants | $89,750 | $45,600 | - |
$89,750
-
gal
|
- | - | - | |
| 03 | 4.431: Train operators for maximum operating efficiency | $7,500 | $5,600 | - | - | - | $7,500 | - | |
| 04 | 2.7131: Add area lighting switches | $6,606 | $10,900 |
$6,606
235,932
kWh
|
- | - | - | - | |
| 05 | 2.7261: Install timers and/or thermostats | $5,830 | $7,750 |
$5,830
208,089
kWh
|
- | - | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,925 | $4,725 |
$4,925
175,850
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $608,611 | $106,575 |
$17,361
619,871
kWh
|
$89,750
-
gal
|
$190,000
-
lb
|
$7,500 | $304,000 | ||
| TOTAL IMPLEMENTED | $5,830 | $7,750 |
$5,830
208,089
kWh
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs