Assessment Year | 1998 |
---|---|
Principal Product | Hardwood lumber |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 79 |
Plant Area |
30,000
ft2
|
Annual Production | 20,000
thousand feet
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $39,761 | 2,321,219 |
kWh
|
$0.017 |
Electricity Demand | $39,442 | 6,969 |
kW-mo/yr
|
$5.66 |
Electricity Fees | $28,988 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $376,505 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $73,365 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.445: Install equipment to move product | $65,150 | $545,645 | - | - | - | $58,750 | - | $6,400 | |
02 | 3.6123: Burn wood by-products for heat | $237,780 | $900,000 |
$142,900
6,424,385
kWh
|
- |
$200,000
-
lb
|
$(-105,120.0) | - | - | |
03 | 3.7212: Improved material handling (mixing and transfer) | $60,120 | $116,240 | - | - |
$60,120
-
lb
|
- | - | - | |
04 | 3.8136: Switch to a solvent that can be cleaned and re-used | $9,965 | $5,000 | - | - | - | - | $9,965 | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,380 | $6,370 |
$550
32,532
kWh
|
$1,830
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $900 | - |
$900
53,048
kWh
|
- | - | - | - | - | |
07 | 2.7261: Install timers and/or thermostats | $210 | $465 |
$210
12,309
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $376,505 | $1,573,720 |
$144,560
6,522,274
kWh
|
$1,830
-
kW-mo/yr
|
$260,120
-
lb
|
$(-46,370.0) | $9,965 | $6,400 | ||
TOTAL IMPLEMENTED | $73,365 | $127,610 |
$1,450
85,580
kWh
|
$1,830
-
kW-mo/yr
|
$60,120
-
lb
|
- | $9,965 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs