ITAC Assessment: TN0619
ITAC logo
ITAC Assessment: TN0619
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Seat belt fabric
NAICS
n/a
SIC 2399: Fabricated Textile Products, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 480
Plant Area 219,000
ft2
Annual Production 300,000,000
thousand feet
Production Hrs. Annual 6,600
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $751,038 24,721,571
kWh
Electricity Demand $446,985 47,770
kW-mo/yr
Electricity Fees $9,572 -
Natural Gas $597,293 181,727
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $729,195 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings Increase in Production Savings
01 4.112: Replace old machine with new automatic multi-station tool $537,700 $66,720 - - - - - $(-102,300.0) $(-20,000.0) - - $660,000
02 3.5313: Increase amount of waste recovered for resale $124,950 $40,400 - - - - - $(-17,050.0) $(-20,000.0) - $162,000 -
03 3.3128: Utilize other methods to remove contaminants $46,080 $4,900 - - $23,040
-
Tgal
$4,320
-
gal
- - - $18,720 - -
04 2.7261: Install timers and/or thermostats $8,620 $2,090 $8,620
287,222
kWh
- - - - - - - - -
05 2.2437: Recover waste heat from equipment $4,850 $4,350 $4,850
430,832
kWh
- - - - - - - - -
06 3.7212: Improved material handling (mixing and transfer) $3,345 - - - - - $3,825
-
gal
- $(-1,000.0) $520 - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,820 $4,340 $1,760
58,617
kWh
$1,060
-
kW-mo/yr
- - - - - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $830 $745 $240
7,913
kWh
$590
-
kW-mo/yr
- - - - - - - -
TOTAL RECOMMENDED $729,195 $123,545 $15,470
784,584
kWh
$1,650
-
kW-mo/yr
$23,040
-
Tgal
$4,320
-
gal
$3,825
-
gal
$(-119,350.0) $(-41,000.0) $19,240 $162,000 $660,000
TOTAL IMPLEMENTED - - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs