ITAC Assessment: TN0618
ITAC logo
ITAC Assessment: TN0618
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Dyed textiles
NAICS
n/a
SIC 2269: Finishers of Textiles, Not elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 350,000
ft2
Annual Production 180,000,000
thousand feet
Production Hrs. Annual 6,120
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $440,292 10,676,436
kWh
Electricity Demand $92,511 26,934
kW-mo/yr
Electricity Fees $16,524 -
Natural Gas $953,378 185,482
MMBtu
Fuel Oil #6 $6,436 1,447
MMBtu
Coal $374,213 200,278
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $94,175 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Coal Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings
01 2.2511: Insulate bare equipment $32,090 $46,680 n/a - - $23,430
-
MMBtu
$8,660
-
MMBtu
- - - - - - -
02 2.2514: Cover open tanks $19,880 - n/a - - $12,800
-
MMBtu
$7,080
-
MMBtu
- - - - - - -
03 4.421: Modify current incentive program $16,000 $10,000 n/a - - - - - - - $(-5,000.0) - - $21,000
04 2.2135: Repair and eliminate steam leaks $13,230 $1,960 n/a - - $8,520
-
MMBtu
$4,710
-
MMBtu
- - - - - - -
05 3.5217: Reuse / recycle/ sell paper products $8,415 $6,640 n/a - - - - - $13,335
-
lb
$(-3,640.0) - $(-1,280.0) - -
06 2.4221: Install compressor air intakes in coolest locations $3,200 $990 n/a $2,580
64,478
kWh
$620
-
kW-mo/yr
- - - - - - - - -
07 3.4156: Use flow control valves on equipment to optimize water use $1,360 $540 n/a - - - - $970
-
Tgal
- - - - $390
-
Tgal
-
TOTAL RECOMMENDED $94,175 $66,810 $2,580
64,478
kWh
$620
-
kW-mo/yr
$44,750
-
MMBtu
$20,450
-
MMBtu
$970
-
Tgal
$13,335
-
lb
$(-3,640.0) $(-5,000.0) $(-1,280.0) $390
-
Tgal
$21,000
TOTAL IMPLEMENTED - - - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Coal Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs