ITAC Assessment: TN0610
ITAC logo
ITAC Assessment: TN0610
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product circuit board mounted power supplies
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 276
Plant Area 33,000
ft2
Annual Production 1,144,000
pieces
Production Hrs. Annual 4,862
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,941 1,881,887
kWh
Electricity Demand $25,447 4,239
kW-mo/yr
Electricity Fees $4,810 -
LPG $9,991 785
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $231,345 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
01 4.421: Modify current incentive program $118,000 $10,000 n/a - - - - - $118,000
02 4.445: Install equipment to move product $56,055 $50,060 n/a - - - - $56,055 -
03 3.6193: Install equipment (eg compactor) to reduce disposal costs $32,660 $11,800 n/a $(-100.0)
(-2,052)
kWh
- - $32,760
-
lb
- -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $15,220 $3,600 n/a $(-60.0)
(-1,172)
kWh
- - $17,360
-
lb
$(-2,080.0) -
05 2.6232: Install set-back timers $7,910 $3,520 n/a $5,970
165,885
kWh
- $1,940
-
MMBtu
- - -
06 2.7111: Reduce illumination to minimum necessary levels $630 $250 n/a $340
9,379
kWh
$290
-
kW-mo/yr
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $525 $1,120 n/a $305
8,499
kWh
$220
-
kW-mo/yr
- - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $345 $250 n/a $200
5,569
kWh
$145
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $231,345 $80,600 $6,655
186,108
kWh
$655
-
kW-mo/yr
$1,940
-
MMBtu
$50,120
-
lb
$53,975 $118,000
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs