| Assessment Year | 1997 |
|---|---|
| Principal Product | Automotive exhuast components |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $100 M to 500M |
| # of Employees | 880 |
| Plant Area |
625,000
ft2
|
| Annual Production | 10,000,000
pieces
|
| Production Hrs. Annual | 6,600
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $750,057 | 23,873,388 |
kWh
|
$0.031 |
| Electricity Demand | $512,783 | 49,904 |
kW-mo/yr
|
$10.28 |
| Electricity Fees | $19,146 | - |
|
- |
| Natural Gas | $394,987 | 55,804 |
MMBtu
|
$7.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $881,900 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $881,900 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.611: Begin a practice of predictive / preventative maintenance | $333,410 | - | - | - | - | - | $(-76,700.0) | $2,110 | $(-8,500.0) | $416,500 | |
| 02 | 4.122: Develop standard procedures to improve internal yields | $327,397 | - | - | - | - |
$(-14,618.0)
-
lb
|
- | $102,615 | - | $239,400 | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $83,573 | $108,500 |
$83,573
2,611,665
kWh
|
- | - | - | - | - | - | - | |
| 04 | 2.7231: Use radiant heater for spot heating | $96,084 | $35,020 | - | - |
$96,084
-
MMBtu
|
- | - | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,339 | $3,000 |
$9,979
311,841
kWh
|
$6,360
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 06 | 2.7131: Add area lighting switches | $11,208 | $13,340 |
$11,208
350,234
kWh
|
- | - | - | - | - | - | - | |
| 07 | 2.7261: Install timers and/or thermostats | $10,349 | $2,016 |
$6,508
203,400
kWh
|
- |
$3,841
-
MMBtu
|
- | - | - | - | - | |
| 08 | 3.5217: Reuse / recycle/ sell paper products | $3,540 | $8,288 |
$(-20.0)
(-586)
kWh
|
- | - |
$8,625
-
lb
|
$(-4,125.0) | - | $(-940.0) | - | |
| TOTAL RECOMMENDED | $881,900 | $170,164 |
$111,248
3,476,554
kWh
|
$6,360
-
kW-mo/yr
|
$99,925
-
MMBtu
|
$(-5,993.0)
-
lb
|
$(-80,825.0) | $104,725 | $(-9,440.0) | $655,900 | ||
| TOTAL IMPLEMENTED | $881,900 | $170,164 |
$111,248
3,476,554
kWh
|
$6,360
-
kW-mo/yr
|
$99,925
-
MMBtu
|
$(-5,993.0)
-
lb
|
$(-80,825.0) | $104,725 | $(-9,440.0) | $655,900 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs