ITAC Assessment: HO0063
ITAC logo
ITAC Assessment: HO0063
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Laminated Panels
NAICS
n/a
SIC 3083: Laminated Plastics Plate, Sheet, and Profile Shapes
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 65,000
ft2
Annual Production 400,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,923 487,691
kWh
Natural Gas $27,641 4,956
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,074 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,074

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,957 $1,987 $1,957
22,860
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $570 $1,541 $570
6,741
kWh
03 2.4133: Use most efficient type of electric motors $248 $513 $248
2,931
kWh
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $30 $30 $30
293
kWh
05 2.4221: Install compressor air intakes in coolest locations $269 $500 $269
3,224
kWh
TOTAL RECOMMENDED $3,074 $4,571 $3,074
36,049
kWh
TOTAL IMPLEMENTED $3,074 $4,571 $3,074
36,049
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs