| Assessment Year | 1997 |
|---|---|
| Principal Product | Commercial aluminum-framed windows |
| NAICS |
n/a
|
| SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
| Sales Range | $10 M to 50M |
| # of Employees | 149 |
| Plant Area |
147,000
ft2
|
| Annual Production | 52,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $52,288 | 1,385,111 |
kWh
|
$0.038 |
| Electricity Demand | $30,412 | 5,053 |
kW-mo/yr
|
$6.02 |
| Electricity Fees | $5,350 | - |
|
- |
| Natural Gas | $42,837 | 6,380 |
MMBtu
|
$6.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $449,520 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.445: Install equipment to move product | $155,710 | $69,000 |
$(-90.0)
(-2,931)
kWh
|
$(-200.0)
-
kW-mo/yr
|
- | - | $156,000 | - | - | |
| 02 | 3.1172: Revise raw material specs | $128,770 | - | - | - | - |
$197,000
-
lb
|
$(-70,000.0) | $1,770 | - | |
| 03 | 3.5313: Increase amount of waste recovered for resale | $92,330 | $32,900 | - | - | - |
$7,240
-
lb
|
$35,090 | - | $50,000 | |
| 04 | 3.1172: Revise raw material specs | $50,700 | - | - | - | - |
$50,700
-
lb
|
- | - | - | |
| 05 | 2.7261: Install timers and/or thermostats | $19,720 | $3,400 |
$1,820
58,617
kWh
|
- |
$17,900
-
MMBtu
|
- | - | - | - | |
| 06 | 2.7145: Install skylights | $1,180 | $1,000 |
$1,180
38,101
kWh
|
- | - | - | - | - | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,110 | $1,110 |
$230
7,327
kWh
|
$880
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $449,520 | $107,410 |
$3,140
101,114
kWh
|
$680
-
kW-mo/yr
|
$17,900
-
MMBtu
|
$254,940
-
lb
|
$121,090 | $1,770 | $50,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs