ITAC Assessment: TN0594
ITAC logo
ITAC Assessment: TN0594
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Single and multi-wall bags
NAICS
n/a
SIC 2673: Plastics, Foil, and Coated Paper Bags
Sales Range $50
M
to 100
M
# of Employees 410
Plant Area 640,000
ft2
Annual Production 130,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $295,771 9,923,799
kWh
Electricity Demand $171,932 18,527
kW-mo/yr
Natural Gas $236,469 69,165
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,392,418 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 3.1192: Reduce scrap production $2,603,900 $170,000 - - - $2,603,900
-
lb
- -
02 3.1191: Change procedures / equipment / operating conditions $744,968 $70,400 - - - $713,768
-
lb
$31,200 -
03 2.7124: Make a practice of turning off lights when not needed $25,470 - $15,650
521,688
kWh
$9,820
-
kW-mo/yr
- - - -
04 2.7229: Air condition only space necessary $7,270 $12,400 $(-130.0)
(-4,396)
kWh
- $7,400
-
MMBtu
- - -
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $6,900 - $(-250.0)
(-8,206)
kWh
- - - $(-250.0) $7,400
06 2.4224: Upgrade controls on compressors $2,380 $9,200 $2,380
79,426
kWh
- - - - -
07 2.4314: Use synthetic lubricant $1,530 - $712
23,740
kWh
$818
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $3,392,418 $262,000 $18,362
612,252
kWh
$10,638
-
kW-mo/yr
$7,400
-
MMBtu
$3,317,668
-
lb
$30,950 $7,400
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs