ITAC Assessment: TN0593
ITAC logo
ITAC Assessment: TN0593
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Packaged country hams
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 28,000
ft2
Annual Production 4,000,000
lb
Production Hrs. Annual 2,340
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,230 1,246,776
kWh
Electricity Demand $9,685 1,116
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $160,873 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,594

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings By-product Production Savings
01 4.321: Optimize production lot sizes and inventories $92,395 $100,000 - - - $(-7,605.0) - - $100,000
02 2.4325: Upgrade conveyors $30,420 $14,000 - - - $30,420 - - -
03 3.5313: Increase amount of waste recovered for resale $25,513 $10,000 - - $23,721
-
lb
- $1,792 - -
04 4.211: Consider use / purchase of bulk materials where possible $6,872 $25,000 - - $375
-
lb
- - $6,497 -
05 2.7124: Make a practice of turning off lights when not needed $2,668 - $1,021
24,912
kWh
$1,647
-
kW-mo/yr
- - - - -
06 3.6192: Use a less expensive method of waste removal $1,506 - - - - - $1,506 - -
07 2.7447: Install vinyl strip / high speed / air curtain doors $821 $3,000 $409
9,965
kWh
$412
-
kW-mo/yr
- - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $678 $713 $60
1,465
kWh
$618
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $160,873 $152,713 $1,490
36,342
kWh
$2,677
-
kW-mo/yr
$24,096
-
lb
$22,815 $3,298 $6,497 $100,000
TOTAL IMPLEMENTED $34,594 $14,000 $1,021
24,912
kWh
$1,647
-
kW-mo/yr
- $30,420 $1,506 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs