| Assessment Year | 1996 |
|---|---|
| Principal Product | Transmissions and worm gear reducers |
| NAICS |
n/a
|
| SIC | 3566: Speed Changers, Industrial High-Speed Drives, and Gears |
| Sales Range | $5 M to 10M |
| # of Employees | 85 |
| Plant Area |
66,000
ft2
|
| Annual Production | 26,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,597 | 1,187,280 |
kWh
|
$0.056 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,974 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,752 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7144: Install spectral reflectors / delamp | $7,095 | $21,300 |
$6,353
119,871
kWh
|
- | - | - | $742 | |
| 02 | 3.2121: Convert to electrostatic powder coating | $3,817 | $10,480 | - |
$554
-
gal
|
$403 | - | $2,860 | |
| 03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,265 | $6,160 | - | - | $100 | $2,165 | - | |
| 04 | 2.2437: Recover waste heat from equipment | $777 | $2,520 |
$777
14,654
kWh
|
- | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $621 | $1,920 |
$621
11,723
kWh
|
- | - | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $544 | $1,365 |
$544
10,258
kWh
|
- | - | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $404 | $23 |
$404
7,620
kWh
|
- | - | - | - | |
| 08 | 2.4314: Use synthetic lubricant | $311 | - |
$311
5,862
kWh
|
- | - | - | - | |
| 09 | 2.7122: Disconnect ballasts | $140 | $184 |
$140
2,638
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $15,974 | $43,952 |
$9,150
172,626
kWh
|
$554
-
gal
|
$503 | $2,165 | $3,602 | ||
| TOTAL IMPLEMENTED | $9,752 | $27,128 |
$9,010
169,988
kWh
|
- | - | - | $742 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs