Assessment Year | 1996 |
---|---|
Principal Product | Motor actuators and thermal controls |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 290 |
Plant Area |
93,000
ft2
|
Annual Production | 9,000,000
pieces
|
Production Hrs. Annual | 5,400
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $145,654 | 5,611,372 |
kWh
|
$0.026 |
Electricity Demand | $62,499 | 12,068 |
kW-mo/yr
|
$5.18 |
Natural Gas | $9,786 | 1,928 |
MMBtu
|
$5.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $168,886 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $167,561 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1163: Use plastic pallets instead of wood | $162,200 | $297,300 | - | - | - | - | - | $162,200 | - | |
02 | 3.5316: Contract a wood pallet recycling company | $2,400 | - | - | - | - | - | - | $2,400 | - | |
03 | 2.2437: Recover waste heat from equipment | $2,321 | $8,150 | - | - |
$2,321
-
MMBtu
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,325 | $260 |
$703
31,946
kWh
|
$622
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 3.5313: Increase amount of waste recovered for resale | $640 | $1,120 |
$(-500.0)
(-22,274)
kWh
|
- | - |
$250
-
lb
|
$(-750.0) | - | $1,640 | |
TOTAL RECOMMENDED | $168,886 | $306,830 |
$203
9,672
kWh
|
$622
-
kW-mo/yr
|
$2,321
-
MMBtu
|
$250
-
lb
|
$(-750.0) | $164,600 | $1,640 | ||
TOTAL IMPLEMENTED | $167,561 | $306,570 |
$(-500.0)
(-22,274)
kWh
|
- |
$2,321
-
MMBtu
|
$250
-
lb
|
$(-750.0) | $164,600 | $1,640 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs