ITAC Assessment: TN0589
ITAC logo
ITAC Assessment: TN0589
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Oven and BBQ grills
NAICS
n/a
SIC 3631: Household Cooking Equipment
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 60,000
ft2
Annual Production 3,000,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,713 2,590,856
kWh
Electricity Demand $45,539 6,139
kW-mo/yr
Natural Gas $14,337 2,306
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,005 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,430

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.7261: Install timers and/or thermostats $7,441 $2,160 $2,022
67,409
kWh
- $5,419
-
MMBtu
-
02 2.7243: Improve air circulation with destratification fans / other methods $1,430 $2,280 - - $1,430
-
MMBtu
-
03 3.5248: Separate and recycle scrap metal to foundry or for sale $527 $636 - - - $527
-
lb
04 2.7142: Utilize higher efficiency lamps and/or ballasts $477 $90 $44
1,465
kWh
$433
-
kW-mo/yr
- -
05 2.6218: Turn off equipment when not in use $130 $260 $130
4,396
kWh
- - -
TOTAL RECOMMENDED $10,005 $5,426 $2,196
73,270
kWh
$433
-
kW-mo/yr
$6,849
-
MMBtu
$527
-
lb
TOTAL IMPLEMENTED $1,430 $2,280 - - $1,430
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs