Assessment Year | 1998 |
---|---|
Principal Product | Finished Fabrics |
NAICS |
n/a
|
SIC | 2394: Canvas and Related Products |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
89,000
ft2
|
Annual Production | 120,000
thousand feet
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $372,950 | 4,076,788 |
kWh
|
$0.091 |
Electricity Demand | $197,531 | 12,646 |
kW-mo/yr
|
$15.62 |
Natural Gas | $783,606 | 171,836 |
MMBtu
|
$4.56 |
Fuel Oil #6 | $94,320 | 38,975 |
MMBtu
|
$2.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $315,261 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,106 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $263,073 | $1,000,000 |
$222,000
3,701,055
kWh
|
$171,820
-
kW-mo/yr
|
$(-181,127.0)
-
MMBtu
|
$50,380
-
MMBtu
|
- | |
02 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $16,538 | $30,400 |
$(-70.0)
(-1,172)
kWh
|
$(-422.0)
-
kW-mo/yr
|
$10,757
-
MMBtu
|
$6,273
-
MMBtu
|
- | |
03 | 2.4322: Use or replace with energy efficient substitutes | $20,197 | $21,808 |
$(-9,186.0)
(-153,576)
kWh
|
$(-4,702.0)
-
kW-mo/yr
|
$21,530
-
MMBtu
|
$12,555
-
MMBtu
|
- | |
04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $12,411 | $10,638 |
$(-88.0)
(-1,465)
kWh
|
$(-78.0)
-
kW-mo/yr
|
$7,943
-
MMBtu
|
$4,634
-
MMBtu
|
- | |
05 | 3.1191: Change procedures / equipment / operating conditions | $1,568 | - | - | - | - | - |
$1,568
-
lb
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,474 | $5,800 |
$1,474
24,619
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $315,261 | $1,068,646 |
$214,130
3,569,461
kWh
|
$166,618
-
kW-mo/yr
|
$(-140,897.0)
-
MMBtu
|
$73,842
-
MMBtu
|
$1,568
-
lb
|
||
TOTAL IMPLEMENTED | $18,106 | $30,400 |
$(-70.0)
(-1,172)
kWh
|
$(-422.0)
-
kW-mo/yr
|
$10,757
-
MMBtu
|
$6,273
-
MMBtu
|
$1,568
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs