Assessment Year | 1996 |
---|---|
Principal Product | Hamburger and hot dog buns |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
100,000
ft2
|
Annual Production | 28,000,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $135,369 | 4,355,217 |
kWh
|
$0.031 |
Electricity Demand | $69,342 | 8,000 |
kW-mo/yr
|
$8.67 |
Natural Gas | $168,224 | 43,182 |
MMBtu
|
$3.90 |
LPG | $14,218 | 2,430 |
MMBtu
|
$5.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $736,127 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $715 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1182: Make a new by-product | $723,960 | $390,800 | - | - | - | - |
$(-47,040.0)
-
lb
|
$(-75,000.0) | $(-50,000.0) | $896,000 | |
02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $9,110 | $16,600 |
$(-50.0)
(-1,758)
kWh
|
- | - | - |
$9,410
-
lb
|
$(-250.0) | - | - | |
03 | 2.1221: Replace obsolete burners with more efficient ones | $1,824 | $3,000 | - | - |
$1,682
-
MMBtu
|
$142
-
MMBtu
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $715 | $260 |
$378
12,603
kWh
|
$337
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $329 | $300 | - | - |
$329
-
MMBtu
|
- | - | - | - | - | |
06 | 2.2122: Install / repair insulation on condensate lines | $189 | $236 | - | - |
$189
-
MMBtu
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $736,127 | $411,196 |
$328
10,845
kWh
|
$337
-
kW-mo/yr
|
$2,200
-
MMBtu
|
$142
-
MMBtu
|
$(-37,630.0)
-
lb
|
$(-75,250.0) | $(-50,000.0) | $896,000 | ||
TOTAL IMPLEMENTED | $715 | $260 |
$378
12,603
kWh
|
$337
-
kW-mo/yr
|
- | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs