Assessment Year | 1996 |
---|---|
Principal Product | Colored envelopes, specialty cards and envelope and card pac |
NAICS |
n/a
|
SIC | 2771: Greeting Cards |
Sales Range | $50 M to 100M |
# of Employees | 260 |
Plant Area |
192,000
ft2
|
Annual Production | 1,400,000,000
pieces
|
Production Hrs. Annual | 6,960
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $150,525 | 4,565,065 |
kWh
|
$0.033 |
Electricity Demand | $94,527 | 10,956 |
kW-mo/yr
|
$8.63 |
Natural Gas | $13,576 | 2,933 |
MMBtu
|
$4.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,764 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,435 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $11,520 | $13,320 | - |
$11,520
-
kW-mo/yr
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,933 | $2,100 |
$781
25,205
kWh
|
$1,152
-
kW-mo/yr
|
- | - | - | |
03 | 2.8113: Purchase gas directly from a contract gas supplier | $1,358 | - | - | - |
$1,358
-
MMBtu
|
- | - | |
04 | 2.4314: Use synthetic lubricant | $748 | - |
$518
16,706
kWh
|
$230
-
kW-mo/yr
|
- | - | - | |
05 | 3.8211: Convert to aqueous cleaning system | $687 | $1,600 | - | - | - |
$870
-
gal
|
$(-183.0) | |
06 | 2.4221: Install compressor air intakes in coolest locations | $518 | $600 |
$345
11,137
kWh
|
$173
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $16,764 | $17,620 |
$1,644
53,048
kWh
|
$13,075
-
kW-mo/yr
|
$1,358
-
MMBtu
|
$870
-
gal
|
$(-183.0) | ||
TOTAL IMPLEMENTED | $1,435 | $1,600 |
$518
16,706
kWh
|
$230
-
kW-mo/yr
|
- |
$870
-
gal
|
$(-183.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs