ITAC Assessment: OK1060
ITAC logo
ITAC Assessment: OK1060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Cosmetic & hygiene products
NAICS 325611: Soap and Other Detergent Manufacturing
SIC 2844: Perfumes, Cosmetics, and Other Toilet Preparations
Sales Range $1
M
to 5
M
# of Employees 52
Plant Area 200,000
ft2
Annual Production 1,716,000
units
Production Hrs. Annual 2,340
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,182 757,580
kWh
Electricity Fees $708 -
Natural Gas $16,147 2,563
MMBtu
Waste Disposal Costs
Water Usage $7,375 1,715
Tgal
Water Disposal $3,430 1,715
Tgal
TOTAL YEARLY COSTS $95,842
RECOMMENDED SAVINGS* $17,209 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $471

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $445 $1,989 $445
4,942
kWh
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $13,541 $11,594 $13,541
150,458
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $471 - $471
5,237
kWh
- -
04 2.8117: Install sub-metering equipment $2,400 $992 - - $2,400
05 2.3212: Optimize plant power factor $352 $1,500 - $352 -
TOTAL RECOMMENDED $17,209 $16,075 $14,457
160,637
kWh
$352 $2,400
TOTAL IMPLEMENTED $471 - $471
5,237
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs