ITAC Assessment: TN0537
ITAC logo
ITAC Assessment: TN0537
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Tin-coated, steel food containers (cans)
NAICS
n/a
SIC 3411: Metal Cans
Sales Range $50
M
to 100
M
# of Employees 90
Plant Area 125,000
ft2
Annual Production 500,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $115,407 3,541,911
kWh
Natural Gas $78,337 10,280
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,319 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,070

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1113: Reduce combustion air flow to optimum $16,330 $2,190 $1,290
24,326
kWh
$15,040
-
MMBtu
02 2.2437: Recover waste heat from equipment $2,348 $969 - $2,348
-
MMBtu
03 2.2511: Insulate bare equipment $464 $950 - $464
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $827 $528 $827
17,292
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $610 $780 $610
11,430
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $740 $224 $740
7,327
kWh
-
TOTAL RECOMMENDED $21,319 $5,641 $3,467
60,375
kWh
$17,852
-
MMBtu
TOTAL IMPLEMENTED $17,070 $2,414 $2,030
31,653
kWh
$15,040
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs