Assessment Year | 1994 |
---|---|
Principal Product | Platform,dump,and dropframe truck trailers |
NAICS |
n/a
|
SIC | 3715: Truck Trailers |
Sales Range | $50 M to 100M |
# of Employees | 300 |
Plant Area |
160,000
ft2
|
Annual Production | 3,640
pieces
|
Production Hrs. Annual | 4,615
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $266,403 | 3,652,696 |
kWh
|
$0.073 |
Natural Gas | $188,190 | 29,811 |
MMBtu
|
$6.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $504,582 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $501,058 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $25,358 | $11,960 | - |
$25,358
-
MMBtu
|
- | - | - | |
02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $2,818 | $2,816 | - |
$2,818
-
MMBtu
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,717 | - |
$2,717
37,222
kWh
|
- | - | - | - | |
04 | 2.6218: Turn off equipment when not in use | $2,311 | - |
$2,311
31,653
kWh
|
- | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,161 | $2,055 |
$2,161
29,601
kWh
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,869 | $980 |
$1,869
25,498
kWh
|
- | - | - | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $706 | $1,835 |
$706
9,672
kWh
|
- | - | - | - | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $642 | - |
$642
8,792
kWh
|
- | - | - | - | |
09 | 3.2121: Convert to electrostatic powder coating | $442,969 | $62,448 | - | - |
$442,969
-
Tgal
|
- | - | |
10 | 3.8143: Recycle cleaning solvent and reuse | $17,087 | $26,320 | - | - | - |
$17,087
-
gal
|
- | |
11 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,944 | $8,480 | - | - | - | - |
$5,944
-
gal
|
|
TOTAL RECOMMENDED | $504,582 | $116,894 |
$10,406
142,438
kWh
|
$28,176
-
MMBtu
|
$442,969
-
Tgal
|
$17,087
-
gal
|
$5,944
-
gal
|
||
TOTAL IMPLEMENTED | $501,058 | $112,243 |
$9,700
132,766
kWh
|
$25,358
-
MMBtu
|
$442,969
-
Tgal
|
$17,087
-
gal
|
$5,944
-
gal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs