ITAC Assessment: IA0207
ITAC logo
ITAC Assessment: IA0207
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product thermal fixture molds
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 103,000
ft2
Annual Production 10,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $244,072 9,755,276
kWh
Electricity Demand $143,374 22,392
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $172,233 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,014

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $109,522 $345,000 $161,869
6,425,264
kWh
$50,388
-
kW-mo/yr
$(-102,735.0)
-
MMBtu
- - -
02 4.322: Eliminate old stock and modify inventory control $46,000 $12,000 - - - - $46,000 -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,193 $1,348 $4,232
167,937
kWh
$1,961
-
kW-mo/yr
- - - -
04 2.6218: Turn off equipment when not in use $4,781 $4,185 $2,550
101,114
kWh
$2,231
-
kW-mo/yr
- - - -
05 2.4221: Install compressor air intakes in coolest locations $2,212 $82 $1,505
59,789
kWh
$707
-
kW-mo/yr
- - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $828 $25 $566
22,567
kWh
$262
-
kW-mo/yr
- - - -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $2,697 $7,990 - - - $945
-
lb
- $1,752
TOTAL RECOMMENDED $172,233 $370,630 $170,722
6,776,671
kWh
$55,549
-
kW-mo/yr
$(-102,735.0)
-
MMBtu
$945
-
lb
$46,000 $1,752
TOTAL IMPLEMENTED $14,014 $5,640 $8,853
351,407
kWh
$5,161
-
kW-mo/yr
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs