Assessment Year | 1994 |
---|---|
Principal Product | paint |
NAICS |
n/a
|
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $100 M to 500M |
# of Employees | 225 |
Plant Area |
241,000
ft2
|
Annual Production | 16,000
Tgal
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $502,803 | 14,365,768 |
kWh
|
$0.035 |
Natural Gas | $243,040 | 63,958 |
MMBtu
|
$3.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,551 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,298 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $5,985 | $12,000 | - |
$5,985
-
MMBtu
|
|
02 | 2.2163: Use minimum steam operating pressure | $4,260 | - | - |
$4,260
-
MMBtu
|
|
03 | 2.7111: Reduce illumination to minimum necessary levels | $10,416 | $600 |
$10,416
273,447
kWh
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,703 | $1,400 |
$1,703
48,652
kWh
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,652 | $840 |
$1,652
47,186
kWh
|
- | |
06 | 2.4314: Use synthetic lubricant | $1,293 | - |
$1,293
36,928
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $646 | $308 |
$646
18,464
kWh
|
- | |
08 | 2.2511: Insulate bare equipment | $175 | $330 | - |
$175
-
MMBtu
|
|
09 | 2.2511: Insulate bare equipment | $421 | $481 |
$421
12,016
kWh
|
- | |
TOTAL RECOMMENDED | $26,551 | $15,959 |
$16,131
436,693
kWh
|
$10,420
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,298 | $1,148 |
$2,298
65,650
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs