ITAC Assessment: TN0505
ITAC logo
ITAC Assessment: TN0505
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Refigeration fittings and valves
NAICS
n/a
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 88,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $230,628 4,110,492
kWh
Natural Gas $35,618 6,285
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,834 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,299

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $10,734 $4,088 $10,734
191,676
kWh
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $10,127 $730 $10,127
180,832
kWh
-
03 2.7261: Install timers and/or thermostats $4,856 $3,880 $4,497
80,305
kWh
$359
-
MMBtu
04 2.7144: Install spectral reflectors / delamp $6,669 $15,914 $6,669
108,441
kWh
-
05 2.4314: Use synthetic lubricant $5,055 $4,000 $5,055
90,270
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $624 $451 $624
11,137
kWh
-
07 2.6212: Turn off equipment during breaks, reduce operating time $525 $1,380 $525
9,379
kWh
-
08 2.3212: Optimize plant power factor $6,244 $15,800 $6,244
-
kWh
-
TOTAL RECOMMENDED $44,834 $46,243 $44,475
672,040
kWh
$359
-
MMBtu
TOTAL IMPLEMENTED $34,299 $37,912 $34,299
490,328
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs