| Assessment Year | 1993 |
|---|---|
| Principal Product | Plumbing fittings and faucets |
| NAICS |
n/a
|
| SIC | 3432: Plumbing Fixture Fittings and Trim |
| Sales Range | $50 M to 100M |
| # of Employees | 320 |
| Plant Area |
162,000
ft2
|
| Annual Production | 932,600
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $309,004 | 7,830,891 |
kWh
|
$0.039 |
| Natural Gas | $124,075 | 41,762 |
MMBtu
|
$2.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $60,768 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,445 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $9,438 | $3,000 |
$246
6,155
kWh
|
$9,192
-
MMBtu
|
|
| 02 | 2.2511: Insulate bare equipment | $8,307 | $1,125 |
$6,084
152,110
kWh
|
$2,223
-
MMBtu
|
|
| 03 | 2.7144: Install spectral reflectors / delamp | $15,927 | $45,191 |
$15,927
341,735
kWh
|
- | |
| 04 | 2.2135: Repair and eliminate steam leaks | $2,208 | $1,350 | - |
$2,208
-
MMBtu
|
|
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,202 | $1,500 | - |
$2,202
-
MMBtu
|
|
| 06 | 2.2511: Insulate bare equipment | $7,362 | $770 |
$7,362
184,056
kWh
|
- | |
| 07 | 2.3191: Use demand controller or load shedder | $7,140 | $9,600 |
$7,140
178,488
kWh
|
- | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,626 | $3,700 |
$2,626
65,651
kWh
|
- | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,227 | $1,416 |
$2,227
55,686
kWh
|
- | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,383 | $1,856 |
$1,383
34,584
kWh
|
- | |
| 11 | 2.2511: Insulate bare equipment | $318 | $375 | - |
$318
-
MMBtu
|
|
| 12 | 2.4221: Install compressor air intakes in coolest locations | $1,196 | $610 |
$1,196
29,894
kWh
|
- | |
| 13 | 2.4314: Use synthetic lubricant | $235 | $500 |
$235
5,862
kWh
|
- | |
| 14 | 2.6212: Turn off equipment during breaks, reduce operating time | $199 | $330 |
$199
4,982
kWh
|
- | |
| TOTAL RECOMMENDED | $60,768 | $71,323 |
$44,625
1,059,203
kWh
|
$16,143
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $33,445 | $11,392 |
$17,302
432,591
kWh
|
$16,143
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs