| Assessment Year | 1992 |
|---|---|
| Principal Product | PLASTIC EXTRUSIONS |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 55 |
| Plant Area |
n/a
|
| Annual Production | 4,000,000
lb
|
| Production Hrs. Annual | 6,816
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,898 | 1,252,638 |
kWh
|
$0.053 |
| Natural Gas | $6,765 | 1,126 |
MMBtu
|
$6.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,412 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4237: Substitute compressed air cooling with water or air cooling | $3,417 | $3,460 |
$3,417
64,478
kWh
|
- | |
| 02 | 2.7123: Keep lamps and reflectors clean | $3,377 | $5,459 |
$2,730
51,583
kWh
|
$647 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,460 | $30 |
$1,460
27,550
kWh
|
- | |
| 04 | 2.7261: Install timers and/or thermostats | $1,181 | $540 |
$1,181
22,274
kWh
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,258 | $880 |
$1,258
23,740
kWh
|
- | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $606 | - |
$606
11,430
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $880 | $257 |
$1,493
28,136
kWh
|
$(-613.0) | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $233 | $185 |
$233
4,396
kWh
|
- | |
| TOTAL RECOMMENDED | $12,412 | $10,811 |
$12,378
233,587
kWh
|
$34 | ||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs