Assessment Year | 1992 |
---|---|
Principal Product | BREAD AND BUNS |
NAICS |
n/a
|
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
n/a
|
Annual Production | 39,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $133,774 | 2,583,236 |
kWh
|
$0.052 |
Natural Gas | $108,923 | 34,018 |
MMBtu
|
$3.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,954 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,954 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2121: Increase amount of condensate returned | $12,838 | $10,750 | - |
$12,838
-
MMBtu
|
- | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $10,912 | $1,000 | - |
$10,912
-
MMBtu
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,682 | $1,000 |
$2,682
51,583
kWh
|
- | - | |
04 | 2.7123: Keep lamps and reflectors clean | $2,438 | $5,145 |
$2,438
46,893
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,082 | $1,315 |
$1,192
22,860
kWh
|
- | $(-110.0) | |
06 | 2.4221: Install compressor air intakes in coolest locations | $792 | $1,315 |
$792
15,240
kWh
|
- | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,210 | - |
$6,210
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $36,954 | $20,525 |
$13,314
136,576
kWh
|
$23,750
-
MMBtu
|
$(-110.0) | ||
TOTAL IMPLEMENTED | $36,954 | $20,525 |
$13,314
136,576
kWh
|
$23,750
-
MMBtu
|
$(-110.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs