ITAC Assessment: TN0454
ITAC logo
ITAC Assessment: TN0454
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product BREAD AND BUNS
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 39,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $133,774 2,583,236
kWh
Natural Gas $108,923 34,018
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $36,954 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,954

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2121: Increase amount of condensate returned $12,838 $10,750 - $12,838
-
MMBtu
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $10,912 $1,000 - $10,912
-
MMBtu
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,682 $1,000 $2,682
51,583
kWh
- -
04 2.7123: Keep lamps and reflectors clean $2,438 $5,145 $2,438
46,893
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,082 $1,315 $1,192
22,860
kWh
- $(-110.0)
06 2.4221: Install compressor air intakes in coolest locations $792 $1,315 $792
15,240
kWh
- -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $6,210 - $6,210
-
kWh
- -
TOTAL RECOMMENDED $36,954 $20,525 $13,314
136,576
kWh
$23,750
-
MMBtu
$(-110.0)
TOTAL IMPLEMENTED $36,954 $20,525 $13,314
136,576
kWh
$23,750
-
MMBtu
$(-110.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs