ITAC Assessment: TN0440
ITAC logo
ITAC Assessment: TN0440
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product PLASTIC GARMENT HANGERS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 300,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $565,953 12,199,590
kWh
Natural Gas $20,795 4,528
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,757 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $23,728 $710 $23,728
515,827
kWh
-
02 2.6124: Establish equipment maintenance schedule $3,819 - $2,063
44,842
kWh
$1,756
-
MMBtu
03 2.7243: Improve air circulation with destratification fans / other methods $2,084 $7,500 - $2,084
-
MMBtu
04 2.2437: Recover waste heat from equipment $1,173 $1,480 - $1,173
-
MMBtu
05 2.7261: Install timers and/or thermostats $2,953 $1,380 $2,953
64,185
kWh
-
TOTAL RECOMMENDED $33,757 $11,070 $28,744
624,854
kWh
$5,013
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs