| Assessment Year | 2006 |
|---|---|
| Principal Product | Misc. Sheet Metal Work |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
210,000
ft2
|
| Annual Production | 56,250
units
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $210,014 | 2,392,077 |
kWh
|
$0.088 |
| Electricity Demand | $45,216 | 8,040 |
kW-mo/yr
|
$5.62 |
| Natural Gas | $4,631 | 545 |
MMBtu
|
$8.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $80,667 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $67,742 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $55,045 | $24,738 |
$48,806
351,120
kWh
|
$6,239
-
kW-mo/yr
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $540 | $370 |
$510
3,669
kWh
|
$30
-
kW-mo/yr
|
|
| 03 | 2.2511: Insulate bare equipment | $12,153 | $1,123 |
$12,153
87,430
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $232 | $340 |
$185
1,326
kWh
|
$47
-
kW-mo/yr
|
|
| 05 | 2.3212: Optimize plant power factor | $12,697 | $25,000 | - |
$12,697
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $80,667 | $51,571 |
$61,654
443,545
kWh
|
$19,013
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $67,742 | $49,738 |
$48,806
351,120
kWh
|
$18,936
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs