ITAC Assessment: TN0431
ITAC logo
ITAC Assessment: TN0431
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product PRE-COOKED FOOD PRODUCTS
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $10
M
to 50
M
# of Employees 293
Plant Area
n/a
Annual Production 13,700,000
lb
Production Hrs. Annual 5,460
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $497,781 9,837,925
kWh
Natural Gas $148,273 33,772
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,285 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2447: Heat water with exhaust heat $15,356 $31,200 - $15,356
-
MMBtu
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,377 - $2,377
46,600
kWh
-
03 2.7261: Install timers and/or thermostats $2,926 $1,200 $2,926
57,444
kWh
-
04 2.4312: Improve lubrication practices $854 $420 $854
16,706
kWh
-
05 2.2122: Install / repair insulation on condensate lines $290 $25 - $290
-
MMBtu
06 3.6122: Install solid waste incinerator for heat $272 $142 - $272
-
MMBtu
07 2.2511: Insulate bare equipment $210 $335 $210
4,103
kWh
-
TOTAL RECOMMENDED $22,285 $33,322 $6,367
124,853
kWh
$15,918
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs