Assessment Year | 1990 |
---|---|
Principal Product | PHOTO ENLARGERS |
NAICS |
n/a
|
SIC | 3861: Photographic Equipment and Supplies |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
n/a
|
Annual Production | 150
pieces
|
Production Hrs. Annual | 2,444
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,594 | 424,971 |
kWh
|
$0.065 |
Natural Gas | $2,893 | 524 |
MMBtu
|
$5.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,203 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,366 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7123: Keep lamps and reflectors clean | $4,123 | $11,116 |
$3,962
60,961
kWh
|
- | $161 | |
02 | 2.7261: Install timers and/or thermostats | $2,474 | $4,140 |
$1,847
28,429
kWh
|
$627
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,428 | $960 |
$1,428
21,981
kWh
|
- | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,440 | - |
$1,372
21,102
kWh
|
- | $68 | |
05 | 2.7226: Use computer programs to optimize hvac performance | $925 | - |
$925
14,361
kWh
|
- | - | |
06 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $880 | $500 |
$880
13,482
kWh
|
- | - | |
07 | 2.6242: Minimize operation of equipment maintained in standby condition | $780 | $660 |
$780
12,016
kWh
|
- | - | |
08 | 2.7122: Disconnect ballasts | $96 | - |
$96
1,465
kWh
|
- | - | |
09 | 2.4312: Improve lubrication practices | $57 | $30 |
$57
879
kWh
|
- | - | |
TOTAL RECOMMENDED | $12,203 | $17,406 |
$11,347
174,676
kWh
|
$627
-
MMBtu
|
$229 | ||
TOTAL IMPLEMENTED | $11,366 | $16,716 |
$10,510
161,781
kWh
|
$627
-
MMBtu
|
$229 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs