ITAC Assessment: TN0396
ITAC logo
ITAC Assessment: TN0396
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product DENIM JEANS
NAICS
n/a
SIC 2325: Men's and Boys' Separate Trousers and Slacks
Sales Range $500
k
to 1
M
# of Employees 300
Plant Area
n/a
Annual Production 145,000
pieces
Production Hrs. Annual 2,091
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $51,642 1,145,076
kWh
Natural Gas $4,669 849
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,044 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,694

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7123: Keep lamps and reflectors clean $5,135 $19,742 $4,445
98,769
kWh
- $690
02 2.2437: Recover waste heat from equipment $770 $1,025 - $770
-
MMBtu
-
03 2.6212: Turn off equipment during breaks, reduce operating time $1,635 - $1,635
36,342
kWh
- -
04 2.6232: Install set-back timers $462 - $462
10,258
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $462 $360 $462
10,258
kWh
- -
06 2.6212: Turn off equipment during breaks, reduce operating time $290 $385 $290
6,448
kWh
- -
07 2.4312: Improve lubrication practices $290 $1,000 $290
6,448
kWh
- -
TOTAL RECOMMENDED $9,044 $22,512 $7,584
168,523
kWh
$770
-
MMBtu
$690
TOTAL IMPLEMENTED $1,694 $1,385 $924
20,516
kWh
$770
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs