Assessment Year | 1990 |
---|---|
Principal Product | FORKLIFTS |
NAICS |
n/a
|
SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
Sales Range | $100 M to 500M |
# of Employees | 320 |
Plant Area |
n/a
|
Annual Production | 7,700
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $322,557 | 6,085,580 |
kWh
|
$0.053 |
Natural Gas | $82,190 | 15,653 |
MMBtu
|
$5.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,614 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,397 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $8,045 | $18,750 | - |
$8,045
-
MMBtu
|
- | |
02 | 2.2153: Close off unneeded steam lines | $3,217 | - | - |
$3,217
-
MMBtu
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,349 | - |
$4,349
82,063
kWh
|
- | - | |
04 | 2.2422: Use waste heat from hot flue gases to generate steam | $1,071 | $2,350 | - |
$1,071
-
MMBtu
|
- | |
05 | 2.7123: Keep lamps and reflectors clean | $2,447 | $7,125 |
$1,487
28,136
kWh
|
- | $960 | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,258 | $600 |
$1,258
23,740
kWh
|
- | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,227 | $690 |
$1,227
23,154
kWh
|
- | - | |
TOTAL RECOMMENDED | $21,614 | $29,515 |
$8,321
157,093
kWh
|
$12,333
-
MMBtu
|
$960 | ||
TOTAL IMPLEMENTED | $18,397 | $29,515 |
$8,321
157,093
kWh
|
$9,116
-
MMBtu
|
$960 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs