ITAC Assessment: TN0389
ITAC logo
ITAC Assessment: TN0389
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product FORKLIFTS
NAICS
n/a
SIC 3537: Industrial Trucks, Tractors, Trailers, and Stackers
Sales Range $100
M
to 500
M
# of Employees 320
Plant Area
n/a
Annual Production 7,700
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $322,557 6,085,580
kWh
Natural Gas $82,190 15,653
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,614 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,397

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7243: Improve air circulation with destratification fans / other methods $8,045 $18,750 - $8,045
-
MMBtu
-
02 2.2153: Close off unneeded steam lines $3,217 - - $3,217
-
MMBtu
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,349 - $4,349
82,063
kWh
- -
04 2.2422: Use waste heat from hot flue gases to generate steam $1,071 $2,350 - $1,071
-
MMBtu
-
05 2.7123: Keep lamps and reflectors clean $2,447 $7,125 $1,487
28,136
kWh
- $960
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,258 $600 $1,258
23,740
kWh
- -
07 2.4221: Install compressor air intakes in coolest locations $1,227 $690 $1,227
23,154
kWh
- -
TOTAL RECOMMENDED $21,614 $29,515 $8,321
157,093
kWh
$12,333
-
MMBtu
$960
TOTAL IMPLEMENTED $18,397 $29,515 $8,321
157,093
kWh
$9,116
-
MMBtu
$960
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs