| Assessment Year | 1990 |
|---|---|
| Principal Product | FORKLIFTS |
| NAICS |
n/a
|
| SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
| Sales Range | $100 M to 500M |
| # of Employees | 320 |
| Plant Area |
n/a
|
| Annual Production | 7,700
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $322,557 | 6,085,580 |
kWh
|
$0.053 |
| Natural Gas | $82,190 | 15,653 |
MMBtu
|
$5.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,614 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,397 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $8,045 | $18,750 | - |
$8,045
-
MMBtu
|
- | |
| 02 | 2.2153: Close off unneeded steam lines | $3,217 | - | - |
$3,217
-
MMBtu
|
- | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,349 | - |
$4,349
82,063
kWh
|
- | - | |
| 04 | 2.2422: Use waste heat from hot flue gases to generate steam | $1,071 | $2,350 | - |
$1,071
-
MMBtu
|
- | |
| 05 | 2.7123: Keep lamps and reflectors clean | $2,447 | $7,125 |
$1,487
28,136
kWh
|
- | $960 | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,258 | $600 |
$1,258
23,740
kWh
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $1,227 | $690 |
$1,227
23,154
kWh
|
- | - | |
| TOTAL RECOMMENDED | $21,614 | $29,515 |
$8,321
157,093
kWh
|
$12,333
-
MMBtu
|
$960 | ||
| TOTAL IMPLEMENTED | $18,397 | $29,515 |
$8,321
157,093
kWh
|
$9,116
-
MMBtu
|
$960 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs