Assessment Year | 1989 |
---|---|
Principal Product | SOLID OAK WOOD FLOORING |
NAICS |
n/a
|
SIC | 2426: Hardwood Dimension and Flooring Mills |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
n/a
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $353,571 | 6,829,719 |
kWh
|
$0.052 |
Wood | $438,000 | 315,362 |
MMBtu
|
$1.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $380,646 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,710 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $342,613 | $1,000,000 |
$353,571
6,829,719
kWh
|
$(-109,508.0)
-
MMBtu
|
$98,550 | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $13,140 | $34,440 | - |
$13,140
-
MMBtu
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $5,681 | $2,167 | - |
$5,681
-
MMBtu
|
- | |
04 | 2.2135: Repair and eliminate steam leaks | $2,083 | $540 | - |
$2,083
-
MMBtu
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,802 | $7,500 |
$7,802
150,059
kWh
|
- | - | |
06 | 2.6122: Adjust vents to minimize energy use | $5,334 | $8,450 |
$5,334
102,579
kWh
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,301 | $120 |
$2,301
44,256
kWh
|
- | - | |
08 | 2.6232: Install set-back timers | $1,524 | - |
$1,524
29,308
kWh
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $168 | $135 |
$168
3,224
kWh
|
- | - | |
TOTAL RECOMMENDED | $380,646 | $1,053,352 |
$370,700
7,159,145
kWh
|
$(-88,604.0)
-
MMBtu
|
$98,550 | ||
TOTAL IMPLEMENTED | $13,710 | $8,160 |
$11,627
223,623
kWh
|
$2,083
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs