| Assessment Year | 1989 |
|---|---|
| Principal Product | SNACK FOODS |
| NAICS |
n/a
|
| SIC | 2052: Cookies and Crackers |
| Sales Range | $50 M to 100M |
| # of Employees | 348 |
| Plant Area |
n/a
|
| Annual Production | 41,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $247,302 | 5,131,888 |
kWh
|
$0.048 |
| Natural Gas | $115,944 | 36,116 |
MMBtu
|
$3.21 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $38,289 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,824 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1212: Operate boilers on high fire setting | $11,558 | $20,160 | - |
$11,558
-
MMBtu
|
- | |
| 02 | 2.7231: Use radiant heater for spot heating | $7,050 | $11,350 | - |
$7,050
-
MMBtu
|
- | |
| 03 | 2.7123: Keep lamps and reflectors clean | $8,465 | $12,145 |
$7,990
166,471
kWh
|
- | $475 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,164 | $180 |
$4,164
86,753
kWh
|
- | - | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $46 | - | - |
$346
-
MMBtu
|
$(-300.0) | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,599 | $1,800 |
$5,599
116,647
kWh
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $1,407 | $540 |
$1,407
29,308
kWh
|
- | - | |
| TOTAL RECOMMENDED | $38,289 | $46,175 |
$19,160
399,179
kWh
|
$18,954
-
MMBtu
|
$175 | ||
| TOTAL IMPLEMENTED | $29,824 | $34,030 |
$11,170
232,708
kWh
|
$18,954
-
MMBtu
|
$(-300.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs