| Assessment Year | 1988 |
|---|---|
| Principal Product | EXTRUDED PAPER BOARD |
| NAICS |
n/a
|
| SIC | 2675: Die-Cut Paper and Paperboard and Cardboard |
| Sales Range | $10 M to 50M |
| # of Employees | 240 |
| Plant Area |
n/a
|
| Annual Production | 300,000
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $923,425 | 19,734,467 |
kWh
|
$0.047 |
| LPG | $259,020 | 59,073 |
MMBtu
|
$4.38 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $132,441 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $128,309 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2444: Use hot process fluids to preheat incoming process fluids | $106,613 | $25,500 |
$42,124
896,249
kWh
|
$64,489
-
MMBtu
|
|
| 03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $7,397 | $14,940 |
$7,397
157,386
kWh
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,130 | $3,800 |
$6,130
130,422
kWh
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $4,132 | $1,055 |
$4,132
87,925
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,880 | $1,800 |
$7,880
167,644
kWh
|
- | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $289 | $30 |
$289
6,155
kWh
|
- | |
| TOTAL RECOMMENDED | $132,441 | $47,125 |
$67,952
1,445,781
kWh
|
$64,489
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $128,309 | $46,070 |
$63,820
1,357,856
kWh
|
$64,489
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs