Assessment Year | 1988 |
---|---|
Principal Product | ELECTRICAL LOAD CENTERS |
NAICS |
n/a
|
SIC | 3613: Switchgear and Switchboard Apparatus |
Sales Range | $50 M to 100M |
# of Employees | 357 |
Plant Area |
n/a
|
Annual Production | 250,000
pieces
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $666,131 | 13,095,545 |
kWh
|
$0.051 |
Natural Gas | $118,410 | 29,265 |
MMBtu
|
$4.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,122 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,811 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $5,964 | $19,684 |
$5,964
116,940
kWh
|
- | |
02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,471 | $2,193 |
$5,471
107,268
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,753 | $615 |
$4,753
93,200
kWh
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,619 | - |
$4,619
90,563
kWh
|
- | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $1,783 | $3,300 |
$1,435
28,136
kWh
|
$348
-
MMBtu
|
|
06 | 2.4221: Install compressor air intakes in coolest locations | $1,824 | $1,180 |
$1,824
35,756
kWh
|
- | |
07 | 2.4312: Improve lubrication practices | $1,824 | - |
$1,824
35,756
kWh
|
- | |
08 | 2.2511: Insulate bare equipment | $1,151 | $566 |
$1,151
22,567
kWh
|
- | |
09 | 2.2511: Insulate bare equipment | $1,106 | $146 |
$1,106
21,688
kWh
|
- | |
10 | 2.2514: Cover open tanks | $252 | - | - |
$252
-
MMBtu
|
|
11 | 2.2511: Insulate bare equipment | $196 | $561 | - |
$196
-
MMBtu
|
|
12 | 2.2521: Isolate steam lines to avoid heating air conditioned areas | $179 | $600 |
$179
3,517
kWh
|
- | |
TOTAL RECOMMENDED | $29,122 | $28,845 |
$28,326
555,391
kWh
|
$796
-
MMBtu
|
||
TOTAL IMPLEMENTED | $21,811 | $8,034 |
$21,211
415,884
kWh
|
$600
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs