ITAC Assessment: TN0324
ITAC logo
ITAC Assessment: TN0324
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product FABRICATED METAL PARTS
NAICS
n/a
SIC 3465: Automotive Stampings
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 1,250,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $155,531 2,842,907
kWh
Natural Gas $5,901 1,280
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,651 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,175

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,756 $300 $3,756
68,288
kWh
-
02 2.2437: Recover waste heat from equipment $906 $585 - $906
-
MMBtu
03 2.4221: Install compressor air intakes in coolest locations $1,612 $4,800 $1,612
29,308
kWh
-
04 2.7111: Reduce illumination to minimum necessary levels $1,386 $2,836 $1,386
25,205
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,322 $1,120 $1,322
24,033
kWh
-
06 2.6122: Adjust vents to minimize energy use $967 - $967
17,585
kWh
-
07 2.4312: Improve lubrication practices $951 $1,500 $951
17,292
kWh
-
08 2.4231: Reduce the pressure of compressed air to the minimum required $822 $1,360 $822
14,947
kWh
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $790 $192 $790
14,361
kWh
-
10 2.7492: Use proper thickness of insulation on building envelope $139 $45 $15
293
kWh
$124
-
MMBtu
TOTAL RECOMMENDED $12,651 $12,738 $11,621
211,312
kWh
$1,030
-
MMBtu
TOTAL IMPLEMENTED $10,175 $8,357 $9,269
168,522
kWh
$906
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs