ITAC Assessment: SF0262
ITAC logo
ITAC Assessment: SF0262
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Canned chili and stew
NAICS 311613: Rendering and Meat Byproduct Processing
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 140,000
ft2
Annual Production 90,000,000
lb
Production Hrs. Annual 6,120
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $410,447 3,650,015
kWh
Electricity Demand $122,086 9,247
kW-mo/yr
Natural Gas $569,925 80,788
MMBtu
LPG $1,223 88
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $210,647 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,007

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.2449: Recover heat from exhausted steam, hot air or hot water $144,108 $26,738 - - $144,108
-
MMBtu
-
02 2.7135: Install occupancy sensors $1,596 $619 $1,287
11,442
kWh
$309
-
kW-mo/yr
- -
03 2.4221: Install compressor air intakes in coolest locations $1,281 $564 $995
8,840
kWh
$286
-
kW-mo/yr
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,464 $5,555 $4,879
43,369
kWh
$1,585
-
kW-mo/yr
- -
05 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $3,013 $2,748 $2,274
20,212
kWh
$739
-
kW-mo/yr
- -
06 2.7134: Use photocell controls $355 $360 $209
1,858
kWh
$146
-
kW-mo/yr
- -
07 2.2511: Insulate bare equipment $2,530 $3,638 - - $2,530
-
MMBtu
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $7,502 $19,608 $6,099
54,211
kWh
$1,403
-
kW-mo/yr
- -
09 2.1224: Replace boiler $39,608 $155,089 - - $39,608
-
MMBtu
-
10 3.4115: Recover and reuse cooling water $4,190 $6,871 - $158
-
kW-mo/yr
- $4,032
-
lb
TOTAL RECOMMENDED $210,647 $221,790 $15,743
139,932
kWh
$4,626
-
kW-mo/yr
$186,246
-
MMBtu
$4,032
-
lb
TOTAL IMPLEMENTED $12,007 $11,941 $7,153
63,581
kWh
$2,324
-
kW-mo/yr
$2,530
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs