ITAC Assessment: TN0315
ITAC logo
ITAC Assessment: TN0315
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product AUTOMOTIVE PARTS
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 9,600,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $360,145 7,233,881
kWh
Natural Gas $25,055 6,358
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,704 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,117

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $5,316 $3,880 - $5,316
-
MMBtu
02 2.2511: Insulate bare equipment $8,265 $346 $8,265
165,299
kWh
-
03 2.2614: Use cooling tower or economizer to replace chiller cooling $5,598 $3,000 $5,598
111,958
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,370 $375 $3,370
67,409
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,491 - $2,491
49,824
kWh
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,568 $280 $1,568
31,360
kWh
-
07 2.2532: Use only amount of air necessary to prevent explosion hazard $1,202 $2,800 $1,202
24,033
kWh
-
08 2.7121: Utilize daylight whenever possible in lieu of artificial light $894 $1,776 $894
17,878
kWh
-
TOTAL RECOMMENDED $28,704 $12,457 $23,388
467,761
kWh
$5,316
-
MMBtu
TOTAL IMPLEMENTED $24,117 $7,881 $18,801
376,026
kWh
$5,316
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs