ITAC Assessment: CO0164
ITAC logo
ITAC Assessment: CO0164
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product FAB. AIRCRAFT PARTS
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area
n/a
Annual Production 53
ton
Production Hrs. Annual 2,470
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,828 276,084
kWh
Natural Gas $8,284 2,035
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,912 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,752

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.8121: Apply for tax-free status for energy purchases $1,010 $250 $1,010
-
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $102 $77 $102
879
kWh
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $860 $570 $860
9,379
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $660 $150 $660
7,327
kWh
05 2.4221: Install compressor air intakes in coolest locations $160 $300 $160
1,758
kWh
06 2.7226: Use computer programs to optimize hvac performance $120 $400 $120
4,689
kWh
TOTAL RECOMMENDED $2,912 $1,747 $2,912
24,032
kWh
TOTAL IMPLEMENTED $2,752 $1,447 $2,752
22,274
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs