Assessment Year | 1987 |
---|---|
Principal Product | AEROSPACE MACHINE PARTS |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 170 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,718
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $111,395 | 1,812,134 |
kWh
|
$0.061 |
LPG | $1,003 | 92 |
MMBtu
|
$10.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,570 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,570 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings |
---|---|---|---|---|---|---|
01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $4,791 | $6,512 |
$4,791
78,546
kWh
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,877 | - |
$1,877
30,774
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $874 | $150 |
$874
14,361
kWh
|
- | |
04 | 2.6232: Install set-back timers | $822 | - |
$822
13,482
kWh
|
- | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $9 | - |
$(-95.0)
(-1,465)
kWh
|
$104
-
MMBtu
|
|
06 | 2.2511: Insulate bare equipment | $197 | $184 |
$197
3,224
kWh
|
- | |
TOTAL RECOMMENDED | $8,570 | $6,846 |
$8,466
138,922
kWh
|
$104
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,570 | $6,846 |
$8,466
138,922
kWh
|
$104
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs