ITAC Assessment: TN0285
ITAC logo
ITAC Assessment: TN0285
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product FINISHED TEXTILE YARN
NAICS
n/a
SIC 2281: Yarn Spinning Mills
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area
n/a
Annual Production 11,252,398
lb
Production Hrs. Annual 6,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $697,717 14,829,133
kWh
Natural Gas $466,178 116,602
MMBtu
Fuel Oil #6 $225,142 48,549
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $82,117 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,361

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #6 Savings Administrative Changes Savings
01 2.2135: Repair and eliminate steam leaks $26,651 $490 - $17,956
-
MMBtu
$8,695
-
MMBtu
-
02 2.2135: Repair and eliminate steam leaks $20,398 $1,400 - $13,744
-
MMBtu
$6,654
-
MMBtu
-
03 2.2136: Install / repair insulation on steam lines $9,667 $1,955 - $6,512
-
MMBtu
$3,155
-
MMBtu
-
04 2.1233: Analyze flue gas for proper air/fuel ratio $6,628 - - $6,928
-
MMBtu
- $(-300.0)
05 2.2511: Insulate bare equipment $4,585 $1,288 - $3,088
-
MMBtu
$1,497
-
MMBtu
-
06 2.7447: Install vinyl strip / high speed / air curtain doors $3,677 $6,720 - $2,480
-
MMBtu
$1,197
-
MMBtu
-
07 3.4156: Use flow control valves on equipment to optimize water use $2,825 $1,480 - $1,904
-
MMBtu
$921
-
MMBtu
-
08 2.2511: Insulate bare equipment $3,692 $1,739 $3,692
78,546
kWh
- - -
09 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $2,479 $1,240 $2,479
52,755
kWh
- - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $1,515 - $1,515
32,239
kWh
- - -
TOTAL RECOMMENDED $82,117 $16,312 $7,686
163,540
kWh
$52,612
-
MMBtu
$22,119
-
MMBtu
$(-300.0)
TOTAL IMPLEMENTED $71,361 $12,045 $1,515
32,239
kWh
$49,524
-
MMBtu
$20,622
-
MMBtu
$(-300.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #6 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs