| Assessment Year | 1986 |
|---|---|
| Principal Product | FINISHED TEXTILE YARN |
| NAICS |
n/a
|
| SIC | 2281: Yarn Spinning Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
n/a
|
| Annual Production | 11,252,398
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $697,717 | 14,829,133 |
kWh
|
$0.047 |
| Natural Gas | $466,178 | 116,602 |
MMBtu
|
$4.00 |
| Fuel Oil #6 | $225,142 | 48,549 |
MMBtu
|
$4.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $82,117 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $71,361 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2135: Repair and eliminate steam leaks | $26,651 | $490 | - |
$17,956
-
MMBtu
|
$8,695
-
MMBtu
|
- | |
| 02 | 2.2135: Repair and eliminate steam leaks | $20,398 | $1,400 | - |
$13,744
-
MMBtu
|
$6,654
-
MMBtu
|
- | |
| 03 | 2.2136: Install / repair insulation on steam lines | $9,667 | $1,955 | - |
$6,512
-
MMBtu
|
$3,155
-
MMBtu
|
- | |
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,628 | - | - |
$6,928
-
MMBtu
|
- | $(-300.0) | |
| 05 | 2.2511: Insulate bare equipment | $4,585 | $1,288 | - |
$3,088
-
MMBtu
|
$1,497
-
MMBtu
|
- | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,677 | $6,720 | - |
$2,480
-
MMBtu
|
$1,197
-
MMBtu
|
- | |
| 07 | 3.4156: Use flow control valves on equipment to optimize water use | $2,825 | $1,480 | - |
$1,904
-
MMBtu
|
$921
-
MMBtu
|
- | |
| 08 | 2.2511: Insulate bare equipment | $3,692 | $1,739 |
$3,692
78,546
kWh
|
- | - | - | |
| 09 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $2,479 | $1,240 |
$2,479
52,755
kWh
|
- | - | - | |
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,515 | - |
$1,515
32,239
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $82,117 | $16,312 |
$7,686
163,540
kWh
|
$52,612
-
MMBtu
|
$22,119
-
MMBtu
|
$(-300.0) | ||
| TOTAL IMPLEMENTED | $71,361 | $12,045 |
$1,515
32,239
kWh
|
$49,524
-
MMBtu
|
$20,622
-
MMBtu
|
$(-300.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #6 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs