| Assessment Year | 1982 |
|---|---|
| Principal Product | STAINLESS STEEL PIPES |
| NAICS |
n/a
|
| SIC | 3498: Fabricated Pipe and Pipe Fittings |
| Sales Range | n/a |
| # of Employees | 250 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 0
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $150,097 | 3,554,220 |
kWh
|
$0.042 |
| Natural Gas | $258,771 | 71,245 |
MMBtu
|
$3.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $50,850 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $7,117 | $5,000 | - |
$7,117
-
MMBtu
|
|
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $36,010 | $16,000 | - |
$36,010
-
MMBtu
|
|
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,005 | - |
$3,005
-
kWh
|
- | |
| 04 | 2.3212: Optimize plant power factor | $4,718 | $2,000 |
$4,718
-
kWh
|
- | |
| TOTAL RECOMMENDED | $50,850 | $23,000 |
$7,723
-
kWh
|
$43,127
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs