Assessment Year | 1982 |
---|---|
Principal Product | STAINLESS STEEL PIPES |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | n/a |
# of Employees | 250 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $150,097 | 3,554,220 |
kWh
|
$0.042 |
Natural Gas | $258,771 | 71,245 |
MMBtu
|
$3.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $50,850 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $7,117 | $5,000 | - |
$7,117
-
MMBtu
|
|
02 | 2.2414: Use waste heat from hot flue gases to preheat | $36,010 | $16,000 | - |
$36,010
-
MMBtu
|
|
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,005 | - |
$3,005
-
kWh
|
- | |
04 | 2.3212: Optimize plant power factor | $4,718 | $2,000 |
$4,718
-
kWh
|
- | |
TOTAL RECOMMENDED | $50,850 | $23,000 |
$7,723
-
kWh
|
$43,127
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs