ITAC Assessment: TA0123
ITAC logo
ITAC Assessment: TA0123
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Drilling Rigs
NAICS 333131: Mining Machinery and Equipment Manufacturing
SIC 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 650
Plant Area 250,000
ft2
Annual Production 300
bbl
Production Hrs. Annual 5,400
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $664,656 24,056
kWh
Electricity Demand $99,424 13,968
kW-mo/yr
Natural Gas $182,347 16,783
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $169,235 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,500

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $148,735 $46,560 $148,735
5,383
kWh
-
02 2.3132: Recharge batteries on during off-peak demand periods $13,420 - - $13,420
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,565 $780 $3,910
142
kWh
$655
-
kW-mo/yr
04 2.7132: Install timers on light switches in little used areas $2,515 $340 $2,515
107
kWh
-
TOTAL RECOMMENDED $169,235 $47,680 $155,160
5,632
kWh
$14,075
-
kW-mo/yr
TOTAL IMPLEMENTED $20,500 $1,120 $6,425
249
kWh
$14,075
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs