Assessment Year | 2006 |
---|---|
Principal Product | Industrial and commercial fan and blower |
NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
98,540
ft2
|
Annual Production | 1,235,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $355,476 | 5,976,408 |
kWh
|
$0.059 |
Electricity Demand | $101,244 | 15,019 |
kW-mo/yr
|
$6.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $73,277 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,987 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,020 | $7,980 |
$18,949
187,800
kWh
|
$2,071
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,208 | $5,065 |
$1,794
17,781
kWh
|
$414
-
kW-mo/yr
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,925 | $9 |
$1,925
19,070
kWh
|
- | |
04 | 2.3132: Recharge batteries on during off-peak demand periods | $478 | - | - |
$478
-
kW-mo/yr
|
|
05 | 2.6218: Turn off equipment when not in use | $2,356 | - |
$2,356
31,045
kWh
|
- | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $45,290 | $22,980 |
$45,290
448,852
kWh
|
- | |
TOTAL RECOMMENDED | $73,277 | $36,034 |
$70,314
704,548
kWh
|
$2,963
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $27,987 | $13,054 |
$25,024
255,696
kWh
|
$2,963
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs