Assessment Year | 2016 |
---|---|
Principal Product | Blow Molded Plastic Parts |
NAICS | 326160: Plastics Bottle Manufacturing |
SIC | 3085: Plastics Bottles |
Sales Range | $10 M to 50M |
# of Employees | 67 |
Plant Area |
121,474
ft2
|
Annual Production | 14,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $731,001 | 16,242,225 |
kWh
|
$0.045 |
Electricity Demand | $271,250 | 29,455 |
kW-mo/yr
|
$9.21 |
Electricity Fees | $64,482 | - |
|
- |
Natural Gas | $48,163 | 8,500 |
MMBtu
|
$5.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,101 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,597 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7122: Disconnect ballasts | $76 | - |
$43
945
kWh
|
$33
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $22,191 | $1,340 |
$22,191
493,136
kWh
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $8,289 | $737 |
$8,289
184,203
kWh
|
- | - | - | |
04 | 2.7314: Reduce ventilation air | $5,800 | $523 |
$441
9,811
kWh
|
$124
-
kW-mo/yr
|
$5,235
-
MMBtu
|
- | |
05 | 3.1161: Eliminate/reduce an operation | $2,255 | $1,215 |
$(-41.0)
(-912)
kWh
|
$(-332.0)
-
kW-mo/yr
|
- | $2,628 | |
06 | 2.2136: Install / repair insulation on steam lines | $231 | $370 | - | - |
$231
-
MMBtu
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $219 | $312 |
$110
2,453
kWh
|
$31
-
kW-mo/yr
|
- | $78 | |
08 | 2.7224: Reduce space conditioning during non-working hours | $181 | $259 | - | - |
$181
-
MMBtu
|
- | |
09 | 2.6211: Conserve energy by efficient use of vending machines | $262 | $591 |
$262
5,820
kWh
|
- | - | - | |
10 | 4.821: Pay bills on time to avoid late fees | $1,597 | - | - | - | - | $1,597 | |
TOTAL RECOMMENDED | $41,101 | $5,347 |
$31,295
695,456
kWh
|
$(-144.0)
-
kW-mo/yr
|
$5,647
-
MMBtu
|
$4,303 | ||
TOTAL IMPLEMENTED | $1,597 | - | - | - | - | $1,597 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs