ITAC Assessment: TA0100
ITAC logo
ITAC Assessment: TA0100
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Industrial Valves
NAICS 332911: Industrial Valve Manufacturing
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 480
Plant Area 255,475
ft2
Annual Production 6,696,936
thousand feet
Production Hrs. Annual 6,032
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $731,685 13,954,914
kWh
Electricity Demand $206,020 35,368
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $179,676 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,860

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $136,425 $38,485 $136,425
2,667,410
kWh
-
02 2.2511: Insulate bare equipment $15,690 $1,015 $15,690
306,750
kWh
-
03 2.7447: Install vinyl strip / high speed / air curtain doors $14,111 $7,705 $14,111
275,908
kWh
-
04 2.7447: Install vinyl strip / high speed / air curtain doors $3,280 $1,485 $3,280
64,156
kWh
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,925 $205 $3,245
63,448
kWh
$680
-
kW-mo/yr
06 2.2511: Insulate bare equipment $2,400 $995 $2,400
47,070
kWh
-
07 2.2511: Insulate bare equipment $1,530 $570 $1,530
29,985
kWh
-
08 2.4238: Do not use compressed air for personal cooling $850 - $460
9,000
kWh
$390
-
kW-mo/yr
09 2.7135: Install occupancy sensors $965 $200 $965
18,877
kWh
-
10 2.7142: Utilize higher efficiency lamps and/or ballasts $500 - $415
8,100
kWh
$85
-
kW-mo/yr
TOTAL RECOMMENDED $179,676 $50,660 $178,521
3,490,704
kWh
$1,155
-
kW-mo/yr
TOTAL IMPLEMENTED $25,860 $2,985 $24,705
483,230
kWh
$1,155
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs