ITAC Assessment: TA0076
ITAC logo
ITAC Assessment: TA0076
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Electronic Connectors
NAICS 334417: Electronic Connector Manufacturing
SIC 3678: Electronic Connectors
Sales Range $10
M
to 50
M
# of Employees 186
Plant Area 32,600
ft2
Annual Production 51,000,000
pieces
Production Hrs. Annual 5,560
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $235,959 4,574,626
kWh
Electricity Demand $84,902 18,365
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $76,523 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,391

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings
01 2.7491: Insulate glazing, walls, ceilings, and roofs $36,101 $25,800 $36,101
500,500
kWh
- - - - -
02 2.4239: Eliminate or reduce compressed air usage $21,003 $12,967 $17,758
245,581
kWh
$3,245
-
kW-mo/yr
- - - -
03 2.8121: Apply for tax-free status for energy purchases $10,113 - - - $10,113 - - -
04 2.6218: Turn off equipment when not in use $3,277 - $3,277
63,274
kWh
- - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,001 $720 $2,603
36,086
kWh
$398
-
kW-mo/yr
- - - -
06 2.6231: Utilize controls to operate equipment only when needed $1,680 $732 $1,473
20,419
kWh
$207
-
kW-mo/yr
- - - -
07 3.5313: Increase amount of waste recovered for resale $880 - - - - $550
-
Tgal
- $330
08 3.5316: Contract a wood pallet recycling company $468 - - - - - $468
-
gal
-
TOTAL RECOMMENDED $76,523 $40,219 $61,212
865,860
kWh
$3,850
-
kW-mo/yr
$10,113 $550
-
Tgal
$468
-
gal
$330
TOTAL IMPLEMENTED $16,391 $720 $5,880
99,360
kWh
$398
-
kW-mo/yr
$10,113 - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs