Assessment Year | 2003 |
---|---|
Principal Product | Machine Drilling Equipment |
NAICS | 333515: Cutting Tool and Machine Tool Accessory Manufacturing |
SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
Sales Range | $50 M to 100M |
# of Employees | 178 |
Plant Area |
200,000
ft2
|
Annual Production | 80
pieces
|
Production Hrs. Annual | 4,463
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $276,826 | 5,951,239 |
kWh
|
$0.047 |
Electricity Demand | $84,200 | 14,788 |
kW-mo/yr
|
$5.69 |
Electricity Fees | $23,195 | - |
|
- |
Natural Gas | $128,692 | 18,744 |
MMBtu
|
$6.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $71,845 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $46,990 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $19,270 | $(-19,270.0) | - | - | $19,270 | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $9,210 | $400 |
$7,450
155,312
kWh
|
$1,760
-
kW-mo/yr
|
- | - | - | |
03 | 2.6218: Turn off equipment when not in use | $8,675 | - | - | - | - |
$8,675
-
MMBtu
|
- | |
04 | 2.4235: Remove or close off unneeded compressed air lines | $7,485 | $480 |
$6,050
126,200
kWh
|
$1,435
-
kW-mo/yr
|
- | - | - | |
05 | 2.4235: Remove or close off unneeded compressed air lines | $6,185 | $485 |
$5,000
104,300
kWh
|
$1,185
-
kW-mo/yr
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,970 | $13,700 |
$5,720
109,896
kWh
|
$1,250
-
kW-mo/yr
|
- | - | - | |
07 | 2.6218: Turn off equipment when not in use | $4,240 | - |
$4,240
88,430
kWh
|
- | - | - | - | |
08 | 2.4156: Establish a preventative maintenance program | $3,960 | $2,510 | - | - | - | - | $3,960 | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,910 | - |
$2,350
49,057
kWh
|
$560
-
kW-mo/yr
|
- | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,940 | $200 |
$2,350
49,025
kWh
|
$590
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $71,845 | $(-1,495.0) |
$33,160
682,220
kWh
|
$6,780
-
kW-mo/yr
|
$19,270 |
$8,675
-
MMBtu
|
$3,960 | ||
TOTAL IMPLEMENTED | $46,990 | $(-15,595.0) |
$19,990
417,012
kWh
|
$3,770
-
kW-mo/yr
|
$19,270 | - | $3,960 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs