Assessment Year | 2003 |
---|---|
Principal Product | Refigeration Components and Chemicals |
NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
180,000
ft2
|
Annual Production | 600,000
pieces
|
Production Hrs. Annual | 3,258
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $123,410 | 2,928,707 |
kWh
|
$0.042 |
Electricity Demand | $41,412 | 9,039 |
kW-mo/yr
|
$4.58 |
Natural Gas | $63,057 | 8,037 |
MMBtu
|
$7.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,654 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,250 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7291: Reschedule and rearrange multiple-source heating systems | $15,460 | - | - | - |
$15,460
-
MMBtu
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,000 | $400 |
$2,180
53,000
kWh
|
$820
-
kW-mo/yr
|
- | - | - | |
03 | 2.7229: Air condition only space necessary | $2,500 | $100 |
$2,500
60,500
kWh
|
- | - | - | - | |
04 | 3.5316: Contract a wood pallet recycling company | $1,800 | - | - | - | - |
$1,800
-
Tgal
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $335 | - |
$245
5,950
kWh
|
$90
-
kW-mo/yr
|
- | - | - | |
06 | 2.7135: Install occupancy sensors | $190 | $123 |
$190
4,635
kWh
|
- | - | - | - | |
07 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $155 | - | - | - | - | - |
$155
-
gal
|
|
08 | 2.4221: Install compressor air intakes in coolest locations | $214 | $120 |
$90
2,173
kWh
|
$124
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $23,654 | $743 |
$5,205
126,258
kWh
|
$1,034
-
kW-mo/yr
|
$15,460
-
MMBtu
|
$1,800
-
Tgal
|
$155
-
gal
|
||
TOTAL IMPLEMENTED | $23,250 | $500 |
$4,925
119,450
kWh
|
$910
-
kW-mo/yr
|
$15,460
-
MMBtu
|
$1,800
-
Tgal
|
$155
-
gal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs